• Updated

There's light at the end of the tunnel as the Bellefontaine Avenue rail crossing should be back up open on Monday evening. Crews will be working through the weekend to get the track in place to make the switch over from the shoe-fly rail to permanent track. Concrete pads have been poured at the crossing and crews are continuing to remove and install rail on the Indiana & Ohio line. The goal is to pave on Monday and open the intersection that evening. Until then, motorists are asked to find a different route to get across town.

  • Updated

Construction is entering another phase at a multi-million dollar grade separation project on Lima's east side. Starting Tuesday, September 3rd, Bellefontaine Avenue will be closed to traffic between Calumet Avenue and Shawnee Street for one week. The Indiana & Ohio Railway will be putting in permanent track at the rail overpass on East Elm Street. The temporary shoe-fly track will be removed and construction of the underpass will continue.