ALLEN COUNTY, OH (WLIO) - The Ohio Department of Transportation has decided on a single-lane roundabout at the intersection of Bluelick Road and State Route 65. This is the roundabout design they picked, which shifted it a little north of the current intersection.

Their decision comes following a public meeting in October and a public comment period. Other alternatives studied were adding turn lanes on Bluelick Road or putting a roundabout northwest of the existing intersection. The construction will not start until the summer of 2027 and is expected to be complete that fall.


Roundabout SR65 and Bluelick Rd

ODOT selects a roundabout as the preferred alternative to improve the intersection at State Route 65 and Bluelick Road north of the city of Lima in Allen County.

November 21, 2024, Press Release from the Ohio Department of Transportation: LIMA, Ohio – The Ohio Department of Transportation (ODOT) is pleased to announce the selection of a roundabout as the preferred alternative to improve the intersection at State Route 65 and Bluelick Road north of the city of Lima in Allen County. The decision follows a public meeting and comment period. 

"Ultimately, the roundabout's ability to significantly enhance safety was the deciding factor," said ODOT District 1 Deputy Director Chris Hughes. "By implementing a roundabout at this intersection, we will also improve traffic flow and provide a smoother commuting experience for the traveling public." 

Following a public meeting on Oct. 3, and subsequent review of stakeholder and public feedback, a conventional single-lane roundabout shifted slightly north of the existing intersection was selected to improve safety and congestion.

Other alternatives studied but not selected were adding turn lanes on Bluelick Road, or constructing a roundabout northwest of the existing intersection.  

Public input revealed a preference for a roundabout or support for modifying the current signalized intersection to include extra turn lanes. No major concerns or unexpected issues were raised regarding any option. 

The project will now advance to the detailed design phase. The tentative schedule is as follows: 

  • Winter 2024/2025 – Spring 2026: Preliminary and detailed design 
  • Fall 2025 – Spring 2027: Right-of-way acquisition  
  • Summer 2027 – Fall 2027: Construction  
 